A315 Hammersmith Road, London, Hammersmith And Fulham
25 November — 27 November
Delays likely Lane closure
Works location: A315
Works description: Network Operations Maintenance:Replace Frame And Cover::Defective Manhole Cover In The C/W
Responsibility for works: UK Power Networks
Current status: Planned work about to start

A4020/A40 Shepherd's Bush Green, London, Hammersmith And Fulham

24 November — 25 November
Delays likely Lane closure
Works location: A4020/A40
Works description: Consequential Damage - Remedial Reinstatement In The Cway
Responsibility for works: Thames Water
Current status: Planned work about to start
A40 Westway, London, Hammersmith And Fulham
24 November — 25 November
Delays likely Lane closure
Works location: A40
Works description: Cpp Block Closure Wb# Testing Lights& Bollards, Bulk Clean & Change, Sweeping, Gully & Beany Block Cleaning, Barrier Works, Grass Cutting, Sign Cleaning, Debris Patrols Nearside Lane Closures With Offside Lane Running - All Vehicle Movements Maintained Eb 23:00 To 05:00 Slip No Nw12-0321
Responsibility for works: Transport For London
Current status: Planned work about to start
A40 Westway, London, Hammersmith And Fulham
24 November — 25 November
Delays likely Lane closure
Works location: A40
Works description: Cpp Block Closure Wb# Testing Lights& Bollards, Bulk Clean & Change, Sweeping, Gully & Beany Block Cleaning, Barrier Works, Grass Cutting, Sign Cleaning, Debris Patrols Nearside Lane Closures With Offside Lane Running - All Vehicle Movements Maintained Wb 23:00 To 05:00 Slip No Nw12-0321
Responsibility for works: Transport For London
Current status: Advanced planning
A4 Hammersmith Flyover, London, Hammersmith And Fulham
24 November — 24 December
Delays likely Road closure
Works location: A4
Works description: Bridge Jacking . Full Closure Of Hammersmith Flyover Eastbound& Westbound
Responsibility for works: Transport For London
Current status: Planned work about to start
Cathnor Road, London, Hammersmith And Fulham
24 November — 26 November
Delays likely Road closure
Works location: -
Works description: -
Responsibility for works: Thames Water
Current status: Planned work about to start
A219 Wood Lane, London, Hammersmith And Fulham
24 November — 30 November
Delays possible Some carriageway incursion
Works location: A219
Works description: Installation Of Telecom Ducts And Chambers In F/W Only - No Impact On C/W
Responsibility for works: City of London Telecomms
Current status: Planned work about to start
A315 Hammersmith Road, London, Hammersmith And Fulham
24 November — 26 November
Delays possible Some carriageway incursion
Works location: A315
Works description: Network Operations Maintenance:Install / Replace Link Box: (Approx Depth 450mm):Remedial Works To Rectify Defect In F/W
Responsibility for works: UK Power Networks
Current status: Planned work about to start
A315 Kensington High Street, London, Kensington And Chelsea
25 November — 26 November
Delays possible Some carriageway incursion
Works location: A315
Works description: District Metering X-Bond - Surface B--Works Intended To Include First Time Permanent Reinstatement Within Same Phase
Responsibility for works: Thames Water
Current status: Planned work about to start
A315 King Street, London, Hammersmith And Fulham
25 November — 27 November
Delays possible Some carriageway incursion
Works location: A315
Works description: Remedial Works Following Defect Inspection - Yorkstone To Go Back In Fwy
Responsibility for works: National Grid Gas Plc
Current status: Planned work about to start
A402 Goldhawk Road, London, Hammersmith And Fulham
24 November — 25 November
Delays possible Some carriageway incursion
Works location: A402
Works description: Interim To Perm Propose In Footway
Responsibility for works: Virgin Media
Current status: Planned work about to start
A402 Goldhawk Road, London, Hammersmith And Fulham
24 November — 27 November
Delays possible Some carriageway incursion
Works location: A402
Works description: 4x25mm Mdpe New Water Supply Connection, Footway And In Carriageway. Ourintention Is To Complete The Permanent Reinstatement In The Same Phase
Responsibility for works: Thames Water
Current status: Planned work about to start
A402 Goldhawk Road, London, Hammersmith And Fulham
24 November — 28 November
Delays possible Some carriageway incursion
Works location: A402
Works description: Connections Small Service:New Service: (Approx Depth 450mm-600mm):Install 2x 100amp 3 Phase Services And Disconnect Exisiting Supply
Responsibility for works: UK Power Networks
Current status: Planned work about to start
Batoum Gardens, London, Hammersmith And Fulham
24 November — 05 December
Delays possible Some carriageway incursion
Works location: -
Works description: -
Responsibility for works: UK Power Networks
Current status: Planned work about to start
Batoum Gardens, London, Hammersmith And Fulham
25 November — 06 December
Delays possible Some carriageway incursion
Works location: -
Works description: -
Responsibility for works: UK Power Networks
Current status: Planned work about to start
Bloemfontein Road, London, Hammersmith And Fulham
24 November — 26 November
Delays possible Some carriageway incursion
Works location: -
Works description: -
Responsibility for works: Thames Water
Current status: Planned work about to start
Commonwealth Avenue, White City Estate, London, Hammersmith And Fulham
24 November — 24 November
Delays possible Some carriageway incursion
Works location: -
Works description: -
Responsibility for works: UK Power Networks
Current status: Planned work about to start
Gayford Road, London, Hammersmith And Fulham
25 November — 26 November
Delays possible Some carriageway incursion
Works location: -
Works description: -
Responsibility for works: Virgin Media
Current status: Planned work about to start
Ravenscourt Road, London, Hammersmith And Fulham
24 November — 01 December
Delays possible Some carriageway incursion
Works location: -
Works description: -
Responsibility for works: Fulcrum Pipelines Limited
Current status: Planned work about to start
Sinclair Road, London, Hammersmith And Fulham
24 November — 24 November
Delays possible Some carriageway incursion
Works location: -
Works description: -
Responsibility for works: UK Power Networks
Current status: Planned work about to start

 

 

 