| A219 Wood Lane, London, Hammersmith And Fulham |
| 10 August — 10 August Traffic control (two-way signals) |
Delays likely due to Streetworks
Replace Sewer Cover--Works Intended To Include First Time Permanent Reinstatement Within Same Phase at A219 |
| Responsibility: Thames Water |
| EToN status: Planned work about to start |
|
|
| A219 Wood Lane, London, Hammersmith And Fulham |
| 10 August — 12 August Lane closure |
Delays likely due to Streetworks
This Permit Is For Thames, Which Will Involve Carrying Out Remedial Works In The Carriageway As Reported By The Ha at A219 |
| Responsibility: Thames Water |
| EToN status: Planned work about to start |
|
|
| A40/A3220 West Cross Route, London, Kensington And Chelsea |
| 11 August — 13 August Road closure |
Delays likely due to Streetworks
Wp Cyclical Routine Maintenance Full Closure & Diversions Nb Closure 1108 Sb Closure 1208 2300 To 0500 Tro Ref Gla 2010 No.144 at A40/A3220 |
| Responsibility: Transport For London |
| EToN status: Planned work about to start |
|
|
| A40 Westway, London, Kensington And Chelsea |
| 10 August — 11 August Lane closure |
Delays likely due to Streetworks
Trial Holes On The Westway Flyover. Single Lane Closure 23.00 To 05.00. Westbound Carriageway at A40 |
| Responsibility: Transport For London |
| EToN status: Planned work about to start |
|
|
| A40 Westway, London, Kensington And Chelsea |
| 11 August — 13 August Lane closure |
Delays likely due to Streetworks
Cpp - These Works Are Batched With Permit Yg400296283. Both Sets Of Works To Take Place Together. Trial Holes On The Westway Flyover. Single Lane Closure 22.30 To 05.00. Eastbound Carriageway at A40 |
| Responsibility: Transport For London |
| EToN status: Planned work about to start |
|
|
|
|
| A219 Shepherd'S Bush Road, London, Hammersmith And Fulham |
| 10 August — 12 August Some carriageway incursion |
Delays possible due to Streetworks
Capital Programmes:Project::Excavation Of Joint Bays, Cable Installation And Reinstatement at A219 |
| Responsibility: UK Power Networks |
| EToN status: Planned work about to start |
|
|
| A315/B408 Glenthorne Road, London, Hammersmith And Fulham |
| 11 August — 13 August Some carriageway incursion |
Delays possible due to Streetworks
Boundary Box Remove In Footway. Our Intention Is To Complete Thepermanent Reinstatement In The Same Phase at A315/B408 |
| Responsibility: Thames Water |
| EToN status: Planned work about to start |
|
|
| A40 Westway, London, Hammersmith And Fulham |
| 10 August — 14 August Some carriageway incursion |
Delays possible due to Streetworks
Uneven Paving Pedestrian Signing Lighting And Guarding Only - No Carriageway Incursion Eb 0800 To 1600 at A40 |
| Responsibility: Transport For London |
| EToN status: Planned work about to start |
|
|
| A4 Talgarth Road, London, Hammersmith And Fulham |
| 11 August — 13 August Some carriageway incursion |
Delays possible due to Streetworks
Repair To A Damaged Network Valve In Footway. Our Intention Is Tocomplete The Permanent Reinstatement In The Same Phase at A4 |
| Responsibility: Thames Water |