|
A3220 Holland Road, London, Kensington And Chelsea |
01 February — 05 February Traffic control (give & take) |
|
|
Delays likely due to Streetworks
Lay New Domestic Service 5m From Main In Carriageway at A3220 |
|
|
Responsibility: National Grid Gas Plc |
|
|
EToN status: Planned work about to start |
|
|
|
|
|
|
|
A40 Westway, London, Hammersmith And Fulham |
01 February — 12 February Road closure |
|
|
Delays likely due to Streetworks
Retaining Wall Contruction - Trief Kerb Construction And Footway Reconstruction - Road Closure Gla/2015/627 - Tman N1501222-001-W001 at A40 |
|
|
Responsibility: Transport For London |
|
|
EToN status: Advanced planning |
|
|
|
|
|
|
|
A40 Westway, London, Hammersmith And Fulham |
01 February — 14 February Road closure |
|
|
Delays likely due to Streetworks
Maintainence Works On Retaining Wall Phase 1 On Slip Road Closure E/B At Junction With Wood Lane. at A40 |
|
|
Responsibility: Transport For London |
|
|
EToN status: Advanced planning |
|
|
|
|
|
|
|
|
|
A3220 Holland Road, London, Kensington And Chelsea |
01 February — 03 February Some carriageway incursion |
|
|
Delays possible due to Streetworks
Customer Side Leakage Supply Pipe Replacement at A3220 |
|
|
Responsibility: Thames Water |
|
|
EToN status: Planned work about to start |
|
|
|
|
|
|
|
A3220 Holland Road, London, Kensington And Chelsea |
02 February — 02 February Some carriageway incursion |
|
|
Delays possible due to Streetworks
Thames Water Need To Carry Out Works On The Water Valve. A Road Narrowing System Will Be Installed To Allow These Works To Be Carried Out. Minor Works, No Excavation. at A3220 |
|
|
Responsibility: Thames Water |
|
|
EToN status: Planned work about to start |
|
|
|
|
|
|
|
A402 Goldhawk Road, London, Hammersmith And Fulham |
01 February — 03 February Some carriageway incursion |
|
|
Delays possible due to Streetworks
Sewer Cover- Re-Bed--Works Intended To Include First Time Permanent Reinstatement Within Same Phase at A402 |
|
|
Responsibility: Thames Water |
|
|
EToN status: Planned work about to start |
|
|
|
|
|
|
|
A4 Talgarth Road, London, Hammersmith And Fulham |
01 February — 03 February Some carriageway incursion |
|
|
Delays possible due to Streetworks
Trial Hole Excavation In Footway. Our Intention Is To Complete Thepermanent Reinstatement In The Same Phase at A4 |
|
|
Responsibility: Thames Water |
|
|
EToN status: Planned work about to start |
|
|
|
|
|
|
|
A4 Talgarth Road, London, Hammersmith And Fulham |
01 February — 12 February Some carriageway incursion |
|
|
Delays possible due to Streetworks
Working On Behalf Of Thames Water To Carry Out Cut And Cap Connection at A4 |
|
|
Responsibility: Thames Water |
|
|
EToN status: Planned work about to start |
|
|
|
|
|
|
|
A4 Talgarth Road, London, Hammersmith And Fulham |
01 February — 12 February Some carriageway incursion |
|
|
Delays possible due to Streetworks
Working On Behalf Of Thames Water To Carry Out Cut And Cap Connection at A4 |
|
|
Responsibility: Thames Water |
|
|
EToN status: Planned work about to start |
|
|
|
|
|
|
|
B408/A315 Glenthorne Road, London, Hammersmith And Fulham |
01 February — 03 February Some carriageway incursion |
|
|
Delays possible due to Streetworks
Build 1 Precast Chamber In 915mm X 445mm X 965mm Deep In Footway,Demolish 1 Existing Jointbox(S) Or Cabinet Base(S),Install 2m Of 1 Way Poly Duct In Footway at B408/A315 |
|
|
Responsibility: BT |
|
|
EToN status: Planned work about to start |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|