Roadworks around Shepherd's Bush
Where to expect traffic delays in the days ahead
|
|
|
|
|
|
A219 Wood Lane, London, Hammersmith And Fulham |
08 June — 10 June |
|
|
Delays possible Some carriageway incursion |
|
Works location: A219 |
|
|
Works description: Hand Dug Trial Hole To Establish Services On Behalf Of O2. All Work Off The Road With Signing And Guarding In Accordance With Chapter 8. 1.2m Footway To Be Maintained For Pedestrians. Full Re-Instatement |
|
|
Responsibility for works: O2 (UK) Limited |
|
|
Current status: Planned work about to start |
|
|
|
|
A4020 Uxbridge Road, London, Hammersmith And Fulham |
09 June — 13 June |
|
|
Delays possible Some carriageway incursion |
|
Works location: A4020 |
|
|
Works description: Main Clamp 0 To 6" In Footway. Our Intention Is To Complete Thepermanent Reinstatement In The Same Phase |
|
|
Responsibility for works: Thames Water |
|
|
Current status: Planned work about to start |
|
|
|
|
A402 Goldhawk Road, London, Hammersmith And Fulham |
08 June — 14 June |
|
|
Delays possible Some carriageway incursion |
|
Works location: A402 |
|
|
Works description: Connections Small Service:Disconnection: (Approx Depth 450mm):Excavate And Expose Mains Cable For Disconnection Of Supply. |
|
|
Responsibility for works: UK Power Networks |
|
|
Current status: Planned work about to start |
|
|
|
|
|
|
Blythe Road, London, Hammersmith And Fulham |
08 June — 13 June |
|
|
Delays possible Some carriageway incursion |
|
Works location: - |
|
|
Works description: - |
|
|
Responsibility for works: Thames Water |
|
|
Current status: Planned work about to start |
|
|
|
Information supplied by Roadworks.org