A3220 Addison Crescent, London, Kensington And Chelsea |
28 July — 03 August |
|
|
Delays likely Traffic control (give & take) |
|
Works location: A3220 |
|
|
Works description: Disconnect 2 X 1" Pe Service From Main In Carriageway |
|
|
Responsibility for works: National Grid Gas Plc |
|
|
Current status: Planned work about to start |
|
|
|
|
A219 Shepherd'S Bush Road, London, Hammersmith And Fulham |
28 July — 01 August |
|
|
Delays possible Some carriageway incursion |
|
Works location: A219 |
|
|
Works description: Main Clamp In Footway. Our Intention Is To Complete The Permanentreinstatement In The Same Phase |
|
|
Responsibility for works: Thames Water |
|
|
Current status: Planned work about to start |
|
|
|
|
A315 Hammersmith Road, London, Hammersmith And Fulham |
29 July — 02 August |
|
|
Delays possible Some carriageway incursion |
|
Works location: A315 |
|
|
Works description: Install 1m Of 1 Way Poly Duct In Footway,Provide 1 Core Drill(S) Into Jointbox Or Building |
|
|
Responsibility for works: BT |
|
|
Current status: Planned work about to start |
|
|
|
|
A315 Hammersmith Road, London, Hammersmith And Fulham |
29 July — 02 August |
|
|
Delays possible Some carriageway incursion |
|
Works location: A315 |
|
|
Works description: Main Clamp In Footway. Our Intention Is To Complete The Permanentreinstatement In The Same Phase |
|
|
Responsibility for works: Thames Water |
|
|
Current status: Planned work about to start |
|
|
|
|
A3220 Addison Crescent, London, Kensington And Chelsea |
28 July — 28 July |
|
|
Delays possible Some carriageway incursion |
|
Works location: A3220 |
|
|
Works description: Thames Water Need To Carry Out Works On The Water Valve. 2 Way Traffic Will Be Maintained At All Times. Minor Works, No Excavation. |
|
|
Responsibility for works: Thames Water |
|
|
Current status: Planned work about to start |
|
|
|
|
A3220 Addison Crescent, London, Kensington And Chelsea |
28 July — 28 July |
|
|
Delays possible Some carriageway incursion |
|
Works location: A3220 |
|
|
Works description: Thames Water Need To Carry Out Works On The Water Valve. 2 Way Traffic Will Be Maintained At All Times. Minor Works, No Excavation. |
|
|
Responsibility for works: Thames Water |
|
|
Current status: Planned work about to start |
|
|
|
|
A3220 Addison Road, London, Kensington And Chelsea |
29 July — 01 August |
|
|
Delays possible Some carriageway incursion |
|
Works location: A3220 |
|
|
Works description: Clear Blocked Duct & Repair Blockages If Found Footway Works Only |
|
|
Responsibility for works: Virgin Media |
|
|
Current status: Planned work about to start |
|
|
|
|
A4020 Uxbridge Road, London, Hammersmith And Fulham |
29 July — 02 August |
|
|
Delays possible Some carriageway incursion |
|
Works location: A4020 |
|
|
Works description: Valve Repack In The Fway & In Carriageway. Our Intention Is Tocomplete The Permanent Reinstatement In The Same Phase |
|
|
Responsibility for works: Thames Water |
|
|
Current status: Planned work about to start |
|
|
|
|
B317 North End Road, London, Hammersmith And Fulham |
29 July — 10 August |
|
|
Delays possible Some carriageway incursion |
|
Works location: B317 |
|
|
Works description: Connections Projects:New Service: (Approx Depth 450mm-600mm):Install Ducting For New Site |
|
|
Responsibility for works: UK Power Networks |
|
|
Current status: Planned work about to start |
|
|
|
|
B415 Elgin Crescent, London, Kensington And Chelsea |
28 July — 02 August |
|
|
Delays possible Some carriageway incursion |
|
Works location: B415 |
|
|
Works description: Lay New Gas Service 2m In F/W |
|
|
Responsibility for works: Fulcrum Pipelines Limited |
|
|
Current status: Planned work about to start |
|
|
|
|
|
|
Blythe Road, London, Hammersmith And Fulham |
29 July — 02 August |
|
|
Delays possible Some carriageway incursion |
|
Works location: - |
|
|
Works description: - |
|
|
Responsibility for works: BT |
|
|
Current status: Planned work about to start |
|
|
|
|
Overstone Road, London, Hammersmith And Fulham |
29 July — 29 July |
|
|
Delays possible Traffic control (Stop/Go boards) |
|
Works location: - |
|
|
Works description: - |
|
|
Responsibility for works: Thames Water |
|
|
Current status: Planned work about to start |
|
|
|
|
Russell Road, London, Kensington And Chelsea |
29 July — 29 July |
|
|
Delays possible Traffic control (Stop/Go boards) |
|
Works location: - |
|
|
Works description: - |
|
|
Responsibility for works: Thames Water |
|
|
Current status: Planned work about to start |
|
|
|