Roadworks around Shepherd's Bush
Where to expect traffic delays in the days ahead
A219 Wood Lane |
01 August — 04 August |
|
|
Delays likely Lane closure |
|
Works description: No excavation. Lane closure for safe access to existing underground structures - fibre cabling for new customer connection. Night working ONLY. On site by 21:00 and off by 06:00. Aplant Survey ref:133-S009138 |
|
|
Responsibility for works: Openreach |
|
|
Current status: Planned work about to start |
|
|
Works reference: BC005CC8W000ONEA248125A1 |
|
|
|
|
A402 Goldhawk Road |
01 August — 04 August |
|
|
Delays likely Road closure |
|
Works description: Carriageway Resurfacing |
|
|
Responsibility for works: Hammersmith and Fulham |
|
|
Current status: Advanced planning |
|
|
Works reference: FE900/PP051 |
|
|
|
|
A40 Shepherd's Bush Green |
01 August — 03 August |
|
|
Delays likely Lane closure |
|
Works description: 11/171 TEL0190355 - Access TfL traffic signal pole 14, F phase red aspect out needs replacing. 22:00-05:00. W/B lane 4. Short stay works, approx 15 mins on site. No noisy works involved |
|
|
Responsibility for works: Transport for London |
|
|
Current status: Planned work about to start |
|
|
Works reference: YG516S000000004048 |
|
|
|
|
Australia Road, White City Estate |
01 August — 04 August |
|
|
Delays likely Road closure |
|
Works description: Carriageway Resurfacing |
|
|
Responsibility for works: Hammersmith and Fulham |
|
|
Current status: Advanced planning |
|
|
Works reference: FE900/PP052 |
|
|
|
|
Westway |
31 July — 02 August |
|
|
Delays likely Road closure |
|
Works description: Cyclical Expansion joint safety checks / maintenance works. |
|
|
Responsibility for works: Transport for London |
|
|
Current status: Planned work about to start |
|
|
Works reference: YG431270478 |
|
|
|
July 31, 2018
Information supplied by roadworks.org