Where to expect delays and diversions in days ahead
Askew Road
02 August — 07 August
Delays likely - Traffic control (two-way signals)
Works description : SEWER CLEANING NON EXCAVATION
Responsibility for works: THAMES WATER
Current status: Planned work about to start
Works reference: MU026002141PNHF--000005
A4020 The Vale, Acton |
Bloemfontein Road |
Brook Green
27 July — 29 September
Delays likely - Lane closure
Works location: From Jct of Aynhoe Road to Jct with Hammersmith Road.
Works description : 287 Ducting installations for fibre Optic connections. Also 4 Toby Boxes and 6 x Chambers will be installed.
Responsibility for works: G. NETWORK COMMUNICATIONS LTD
Current status: Planned work about to start
Works reference: TW03075224629
Broad Passage, Acton |
First Avenue, Acton |
A4020 Uxbridge Road
13 June — 01 August
Delays likely - Lane closure
Works description : CISBOT Internal Mains Sealing long cycle
Responsibility for works: Cadent
Current status: Planned work about to start
Works reference: AZ0071000882065
Information supplied by one.network