Forthcoming Roadworks in Shepherd's Bush


Where to expect delays and diversions in days ahead

Road Closed sign

Uxbridge Road
12 October — 14 October
Delays likely - Lane closure
Works location: NO SECTION 58 RESTRICTIONS ON WORK AREA ADJ 127 TO O/S TELEPHONE EXCHANGE ON, UXBRIDGE ROAD
Works description : Install 14m of 1 way poly duct in Footway
Responsibility for works: Openreach
Current status: Planned work about to start
Works reference:  BC410LO00000500300702702

Coningham Road
12 October — 13 October
Severe delays likely - Road closure
Works location: Coningham Road Junction Uxbridge Road W12 7LL
Works description : Essential Thames Water works to excavate in the C/W to uncover and overhaul leaking critical trunk main valve, back fill and reinstate
Responsibility for works: Thames Water
Current status: Planned work about to start
Works reference:  MU277MV6989109

Wells Road
11 October — 12 October
Severe delays likely - Road closure
Works location: Wells Road - Goldhawk road to Sulgrave Road
Works description : Carriageway Resurfacing
Responsibility for works: Hammersmith and Fulham
Current status: Planned work about to start
Works reference:  FE90014147509

South Africa Road
12 October — 30 October
Delays likely - Lane closure
Works location: From junction with Wood Lane to 201 Wood Lane in f/way and c/way
Works description : Commission a new polyethylene gas supply approximately 25M long from boundary into private
Responsibility for works: Hammersmith and Fulham
Current status: Advanced planning
Works reference:  FE025LBHF_S50_0152_2020

South Africa Road
12 October — 30 October
Delays likely - Lane closure
Works location: From junction with Wood Lane to Troubadour Theatre in f/way and c/way
Works description : Commission a new polyethylene gas supply approximately 25M long
Responsibility for works: Hammersmith and Fulham
Current status: Advanced planning
Works reference:  FE025LBHF_S50_0152C_2020

Shepherd's Bush Road
09 October — 31 October
Delays likely - Lane closure
Works location: o/s Police station
Works description : Connections (Major conn.): Installation of a new electricity supply for a customer: 2x 11kv cable installation
Responsibility for works: UK POWER NETWORKS EASTERN & LONDON
Current status: Planned work about to start
Works reference:  EC40062247819

Shepherd's Bush Green
05 October — 16 October
Delays likely - Lane closure
Works location: o/s. 65- 69 to 70Shepherds Bush Green, W12 8QX
Works description : Connections Projects: Installation of a new electricity supply for a customer: Excavation of a joint Holes and track work for a new service connection.
Responsibility for works: UK POWER NETWORKS EASTERN & LONDON
Current status: Planned work about to start
Works reference:  EC40042284675

Information supplied by  one.network