Forthcoming Roadworks in Shepherd's Bush
Where to expect delays and diversions in days ahead

|
A4020 Uxbridge Road
02 July — 30 July
Delays likely - Lane closure
Works description : CISBOT Internal Mains Sealing long cycle
Responsibility for works: Cadent
Current status: Planned work about to start
Works reference: AZ0071000882065 |
Askew Road
26 July — 31 July
Delays likely - Traffic control (two-way signals)
Works description : SEWER CLEANING NON EXCAVATION
Responsibility for works: THAMES WATER
Current status: Planned work about to start
Works reference: MU026002141PNHF--000004 |
Trussley Road
15 July — 31 July
Delays likely - Road closure
Works description : To lay new duct on behalf of vodafone as agreed with lee currie and ken katende.
Responsibility for works: Vodafone
Current status: Planned work about to start
Works reference: NX502L20JHG272
|
|
A4020 The Vale, Acton
21 July — 10 August
Delays likely - Traffic control (two-way signals)
Works description : CISBOT Internal Mains Sealing long cycle. Cadent are carrying out essential gas remediation works using robotictechnology. This involves internal sealing of joints on large diametercast iron gas mains
Responsibility for works: Cadent
Current status: Planned work about to start
Works reference: AZ0071000882064 |
Bloemfontein Road
25 July — 29 July
Severe delays likely - Road closure
Works location: Bloemfontein road - no 71 to no 93
Works description : Building new Island on the carriageway
Responsibility for works: Hammersmith and Fulham
Current status: Planned work about to start
Works reference: FE90089222174
|
Brook Green
27 July — 29 September
Delays likely - Lane closure
Works location: From Jct of Aynhoe Road to Jct with Hammersmith Road.
Works description : 287 Ducting installations for fibre Optic connections. Also 4 Toby Boxes and 6 x Chambers will be installed.
Responsibility for works: G. NETWORK COMMUNICATIONS LTD
Current status: Planned work about to start
Works reference: TW03075224629
|
Broad Passage, Acton
27 July — 07 August
Severe delays likely - Road closure
Works location: ALONG BROAD PASSAGE - STARTING FOR SECOND AVE,CROSSING FIRST AVE & CONTINUING ALONG BROAD PASSAGE
Works description : INSTALL 2 NEW HV CABLES
Responsibility for works: Scottish and Southern Power Distribution
Current status: Planned work about to start
Works reference: LP551S30004290 |
|
First Avenue, Acton
27 July — 07 August
Severe delays likely - Road closure
Works location: ROAD CROSSING FROM EAST TO WEST FOLLOWING THE ROUTE OF BROAD PASSAGE
Works description : ROAD CROSSING TO INSTALL 2 NEW HV CABLES TO SITE ON BROAD PASSAGE
Responsibility for works: Scottish and Southern Power Distribution
Current status: Planned work about to start
Works reference: LP551S30004289 |
A4020 Uxbridge Road
13 June — 01 August
Delays likely - Lane closure
Works description : CISBOT Internal Mains Sealing long cycle
Responsibility for works: Cadent
Current status: Planned work about to start
Works reference: AZ0071000882065
Information supplied by one.network
|